Windsor Street Water Main Upgrade

This project will improve water service resiliency on the Halifax peninsula

Halifax Water would like to inform you that we are upgrading the water main on Windsor Street, Halifax, between Young Street and Cork Street. This work is part of the utility's 30-year, $4 billion investment commitment to improving aging water, wastewater, and stormwater systems.  

Sackville Trenching will be completing this project on behalf of Halifax Water. The safety of staff, contractors, and the public is our top priority during this work. 

To ensure the safety of our communities and our staff, please maintain a safe distance when Halifax Water staff or contractors are working in your area.

Project Map
Windsor Street Water Main Upgrade Map
What to Expect

During this work, Windsor Street will be closed to all traffic between Young Street and Almon Street. A detour will be in place. The sidewalk will remain open along one side of this work.

Preparation work for this project will begin in mid-July, with the project expected to be complete in mid/late August. Typical hours of work will be 7:00 AM to 7:00 PM, Monday to Friday. 

This work will involve excavation in the street to install the new water main. Following pipe installation, the work areas will be restored – including repaving the impacted sections of the street and any impacted property. See the attached map for the entire project area. Traffic control personnel will be on-site during this construction to manage traffic flows. 

Some customers near this work will be connected to a temporary water supply system to maintain water service during this work. A separate communication will be shared with those customers. During this work, customers in the project area may experience temporary water service disruptions. The contractor will provide advance notice to the impacted customers for any planned water service interruptions. Wastewater and stormwater services will continue throughout this work.

Related Notices
Contact
Cameron Haley
Project Manager, Sackville Trenching
Phone:
902-802-4444
Email:
Eli Levit
Project Manager, Halifax Water
Phone:
782-640-8620
Email: