There are currently no alerts.

Sawmill Creek Storm Sewer Replacement

This project is in partnership with the Halifax Regional Municipality.  

As part of our ongoing commitment to communicating with customers and the local community, Halifax Water would like to inform you that we are beginning work on the Sawmill Creek Daylighting Project. This project is in partnership with the Halifax Regional Municipality.  

Beginning on September 3rd, 2024, the contractor, Dexter Construction will begin installation of the by-pass pipe needed for construction to begin within the creek. Following the installation of the by-pass infrastructure, the contractor will begin installing a series of box culverts, adjacent to the Dundas Street and Alderney Drive intersection.  

Once this portion of the project is complete, it will allow the realignment of the Dundas Street/Alderney Drive/Patuo’qn intersection to begin. In conjunction with the work outlined above, Dexter construction will begin utility adjustments, subgrade work and road reinstatement on Canal Street. Part 1 of this project is expected to be completed in July 2025. The second part of this project will begin in fall of 2025 

This work is part of the utility's 30-year, $4 billion investment commitment to improving aging water, wastewater and stormwater systems.   

To ensure the safety of our communities and our staff, please maintain a safe distance when Halifax Water staff or contractors are working in your area. 

What to Expect

Typical hours of work will be 7:00 AM to 7:00 PM, Monday to Friday. There will be intermittent traffic impacts during Part 1 of the project in 2024, including lane reductions on Alderney Drive. Additional communication notices will be posted when needed regarding specific traffic interruptions and timelines
 
The following milestones will be achieved in two phases: 

Part 1 (September 2024 – December 2024) 

  • By-pass Pipe installation  
  • Box Culvert and stone wall installation 
  • Subgrade work for Patuo’qn and Canal Street 
  • Connection of Alderney Drive/Patuo’qn intersection 

Part 2 (Spring 2025 to Summer 2025)  

  • Asphalt and concrete reinstatement work on Patuo’qn, Alderney Drive and Dundas     Intersection  
  • Subgrade work and Asphalt reinstatement on Canal Street. 
  • Landscaping and sidewalk installation 

Further communications will be provided to the community in 2025 with details on Part 2 and the traffic impacts.

Project Area

Project Area

Contact
Eric Balcom
Project Manager
Phone:
7826416958
Email:
Customer Care
Halifax Water
Phone:
9024209287
Email: